Completed to Date
Overhead utility relocations
Detour and bypass construction
Closed road and opened detour and bypass
Bavarian Inn parking lot and north entrance
Underground utility relocations (85% complete)
Overhead utility relocations
Complete retaining wall
Complete underpass structure
Open WV Route 480 to traffic
Connect Shepherd Grade Road to WV Route 480
Remove bypass use of Bavarian Inn driveway
Complete excavation for west side approach to underpass
Project Schedule
Remove detour at Campus Drive |
|
December 13 |
Connect Campus Drive to WV Route 480 |
|
December 13 |
Complete sidewalks for west side approach to underpass |
|
December 17 |
Restore Bavarian Inn driveway |
|
December 31 |
Complete wall restoration |
|
January 25 |
Clean-up, seeding and closeout |
|
Spring 2013 |
Original Estimated Timeline
February 2012
Begin relocation of utilities (water, sewer, storm sewer, and overhead lines)
March 2012
Begin detour construction
April 2012
Complete utility relocation
Complete detour construction
May 2012
Entrance to Shepherd University West Campus Drive closed
Open parallel temporary detour road to maintain Route 480 throughway to traffic
July 2012
Complete retaining wall, underpass structure and roadway
Open Route 480 to traffic
August 2012
Remove detour at West Campus Drive
Connect West Campus Drive and Shepherd Grade Road to Route 480
Complete excavation and sidewalks on both sides of underpass
Open underpass for pedestrian use
September 2012
Remove detour infrastructure and restore Bavarian Inn property
October 2012
Complete wall restoration, clean-up, seeding and closeout
|